Public Works
Committee Meeting Date:
August 11, 2015
|
City Council Meeting
Date: August 17, 2015
|
Staff Contact: Ted Johnson
|
Petitioner: Tescher Development Group, LLC
|
Location: Homestead Street west of Copperfield
Drive
|
Agenda Title:
|
Authorize
Mayor and Finance Officer to Sign an Agreement between
the City of Rapid City and TESCHER DEVELOPMENT GROUP, LLC, for Homestead
Street 12” Water Main Oversize Cost Reimbursement, not to exceed $27,445.42.
|
Summary:
|
Click here to enter text.An
agreement for oversize cost reimbursement to TESCHER DEVELOPMENT GROUP, LLC,
for the oversizing of approximately 1,000 linear feet of 8-inch water main to
12-inch water main located within the Homestead Street Right-of-Way in the SE¼
NW¼ of Section 4, T1N, R8E, BHM, Pennington County, Rapid City SD. The
proposed water line improvements are being constructed with the Copperfield
Vistas Subdivision Phase 1 and Phase 2 infrastructure improvements. Reimbursement
for the oversize improvements may be requested for Phase 1 or Phase 2
improvements depending on project completion and final acceptance by the
City. Final reimbursement payment shall be determined by actual installed
costs of the improvements, and shall not exceed $27,445.42.
|
Funding Source &
Fiscal Impact (if applicable):
|
Fund
|
Cost
Center
|
|
Fund
|
Cost
Center
|
0834
|
4382
|
|
|
|
|
Recommendation:
|
Action: Approve
oversize cost reimbursement and authorize Mayor and Finance Officer to sign
agreement.
Notes:
|
City Council Options:
|
1) Deny request for reimbursement.
2) Adjust requested reimbursement amount.
|
Attachments &
Links:
|
Oversize Reimbursement Request
|
Original Agreement
|
Location Sketch
|
Cost Estimate
|
|
|
|
|
|
|